Completed

AOP Building of Saiham Knit Composite Ltd.

Project Name: AOP BuildingClient: Saiham Knit Composite Ltd. Single storied factory Building with a Mezzanine floor. Also, there is a Boundary wall, Garage & Rigid Road construction. The length of the building is 340ft and the width is 65ft. The clear height of the floor is 22ft. Project area 22,100 Sft. Architectural Design, Structural Design & Construction work by SRD LIMITED.

AOP Building of Saiham Knit Composite Ltd. Read More »

SRD Monowara Hospital

Monowara Hospital (Pvt.) Ltd.

Monowara Hospital (Pvt) Ltd.: G+13 Storied RCC Building Construction by SRD Limited.This Hospital Building construction was started on 13 March 2019. We used a sheet pile for shore protection for basement work. It has two basements. Used for Masonry work Hollow Block & fair face plaster. This project was ended on 09th July 2021Project Location: 54 Siddheswari Road, Dhaka 1217,

Monowara Hospital (Pvt.) Ltd. Read More »

SRD Saiham Suits Ltd

Prefabricated Steel Warehouse Project of Saiham Suits Ltd.

Prefabricated Steel Warehouse Project: It is a Single storied Prefabricated Steel Structure of 56 feet clear in Height 138 feet in length, 93 ft Wide & area of 12,834 sqft central warehouse. Which was started on 25 April 2019 and was successfully handed over on 10 January 2020. The structure had a connecting bridge linked to the 5-storied

Prefabricated Steel Warehouse Project of Saiham Suits Ltd. Read More »

SRD Saiham Knit Composite Chemical Building

Chemical Store Building of Saiham Knit Composite Ltd.

Project Name: Chemical Store Building Client: Saiham Knit Composite Ltd. Extension of 3rd Floor of Chemical store Building with water roof treatment. Floor area 6300 Sft. Starting Date: 14-August-2021.Handover Date: 26-April-2022 Project Location: Saiham nagar, Noyapara, Madhabpur, Sylhet. Architectural Design, Structural Design & Construction work by SRD LIMITED

Chemical Store Building of Saiham Knit Composite Ltd. Read More »

Saiham Knit Composite Ltd. Truck Weight Scale Installation Project​

Truck Weight Scale Installation Project of Saiham Knit Composite Ltd.

Project Name: Truck Weight Scale InstallationClient: Saiham Knit CompositeLtd. Weighing scales and systems can help textile manufacturers improve efficiency by measuring incoming raw materialsmonitoring each manufacturing stage and weighing the finished product’s outgoing bales.R.C.C Base Casting area 715 ftScale size 45.5′ * 9.5′ *1.33′

Truck Weight Scale Installation Project of Saiham Knit Composite Ltd. Read More »

SRD Niagara Textile Ltd Building

7-Storied RCC Building Retrofitting of Niagara Textile Limited.

We started RCC Building Retrofitting at the 7-storied Garments Building of Niagara Textiles LTD in October 2018 & completed it within February 2019. Under this project, we did Foundation Retrofitting, Column Retrofitting & Beam Retrofitting Works. We did all the work while production was on with proper safety. This was an RSC (ACCORD) Based Project for which we successfully

7-Storied RCC Building Retrofitting of Niagara Textile Limited. Read More »

SRD Niagara Textile Ltd ETP

ETP Construction Project of Niagara Textile Ltd.

Chemical ETP tank of Niagara Textile Limited: It’s a 1,450 Cubic Meter RCC ETP Construction Wor which works started in April 2019 & successfully completed within December 2019. The work was maintained with proper ratio, slum, and clear cover as per drawing.Project Location: Chandra Circle, Kaliakair, Gazipur, Bangladesh Design, Drawing & Construction by SRD Limited.

ETP Construction Project of Niagara Textile Ltd. Read More »

Prefabricated Roof Top Classroom and Computer Lab Extension Project of Dhaka University

Prefabricated Roof Top Classroom and Computer Lab Extension Project: At the Faculty of Business Studies Building, over ten stories we constructed a Steel Structure for the purpose of a rooftop classroom and computer lab. We started the work on 11 May 2019 and successfully built the Steel Structure on 14 February 2020. We did the Interior

Prefabricated Roof Top Classroom and Computer Lab Extension Project of Dhaka University Read More »

RCC Building Retrofitting Project of KAC Fashion Wear Ltd.

RCC Building Retrofitting Project: This RCC Retrofitting Work started on 14 March 2019. In the RCC part, there was Foundation Retrofitting, Column Retrofitting, and Beam Retrofitting. We completed the work while production was running with proper safety & successfully completed it on 15 September 2019. This was an RSC (ACCORD) Based Project for which we got

RCC Building Retrofitting Project of KAC Fashion Wear Ltd. Read More »

Steel Truss Shed Retrofitting Project Of KAC Fashion Wear Ltd.

Steel Truss Shed Retrofitting Project: This Steel Truss Retrofitting Work started on 14 March 2019. In the Steel part, there was Steel Truss Retrofitting. We completed the work while production was running with proper safety & completed it on 15 September 2019. This was an RSC (ACCORD) Based Project for which we got approval.Project Location: 2/13

Steel Truss Shed Retrofitting Project Of KAC Fashion Wear Ltd. Read More »

Rigid Pavement Construction & RCC Pipe Laying of Dhaka North City Corporation

Rigid Pavement Construction & RCC Pipe Laying: We started this project on 14 February 2020. We worked on the Replacement of the 3 feet diagram Drainage RCC pipe, Reconstruction of Pit & CC Road Construction. All the materials were BUET Standard. The Project was handed over on 08 July 2020.Project Location: Kakoli Road, Mirpur, Dhaka, Bangladesh

Rigid Pavement Construction & RCC Pipe Laying of Dhaka North City Corporation Read More »

Underground Water Reservoir & Rain Water Harvesting Tank of Bengal Hurricane Group

Underground Water Reservoir & Rain Water Harvesting Tank: This RCC Construction Project started on 27 June 2020. The water tank had two chambers – one for Reservoir and another for Rainwater harvesting. The depth of the tank was 20 feet. During earth excavation work, we used shore protection to save side soil sliding. Due to heavy

Underground Water Reservoir & Rain Water Harvesting Tank of Bengal Hurricane Group Read More »

RCC Retrofitting & Prefabricated Steel Building Project of Comfit Composite Knit Limited.

RCC Retrofitting & Prefabricated Steel Building Project: We started this project on 14 March 2019. We dismantled the Existing Steel Structure and then we did Pedestal RCC Column Retrofitting Work & the Installation of the Prefabricated Steel Building. We successfully handed over the project on 15 September 2019.This was an RSC (ACCORD) Based Project for which

RCC Retrofitting & Prefabricated Steel Building Project of Comfit Composite Knit Limited. Read More »

G+5 Storied RCC Building Retrofitting & Vertical Extension Project Of Pride Group

G+5 Retrofitting Work at Building 1: We started our retrofitting work at Building 1 on 12 August 2020 and handed it over on 09 April 21. In this structure, we did Foundation Retrofitting, Grade Beam Retrofitting, Column Retrofitting, and Beam Retrofitting while production was running. We did all the work on the running floor with proper

G+5 Storied RCC Building Retrofitting & Vertical Extension Project Of Pride Group Read More »

G+6 Storied RCC Building Retrofitting & Vertical Extension Project Of Pride Group

G+6 Retrofitting Work at Building 2: We started our retrofitting project at Building 2 on 23 October 2018 and handed it over on 09 June 2020. It’s a 5-storied building. In this building, we did Foundation Retrofitting, Grade Beam Retrofitting, Column Retrofitting, and Beam Retrofitting. Each floor area was 22,000 sft. We did all the work

G+6 Storied RCC Building Retrofitting & Vertical Extension Project Of Pride Group Read More »

Generator Building Retrofitting Project of Pride Group

Generator Building Retrofitting: We started our retrofitting work at Generator Building on 12 August 2020. In this structure we did Foundation retrofitting, Grade Beam retrofitting, Column retrofitting, and beam retrofitting while production was running. We did all the work on running the floor with proper safety. This was RSC (ACCORD) Based Project. Project Location: Ulail, Savar, Dhaka,

Generator Building Retrofitting Project of Pride Group Read More »

Knitting Building Project of Saiham Knit Composite Ltd.

Three Storied Knitting Building Project of Saiham Knit Composite Ltd. The area of the building is 49,833Sft. Each Floor has 16,611 sqft (147 x113) and floor height is 12ft, 17ft, 17ft. The construction work started on 18-10-2021 & the work is ongoing. Project Location : Saihamnagar, Noyapara, Madhabpur, Sylhet. Architectural Design, Structural Design & Construction